Home :: About Us :: Director Profile :: Products :: Services :: Join Us :: Feedback form |
|||||
Drive Assembly A well-sized pillow block assembly containing bearings and shaft is supported by a solid carbon steel support rigidly attached to the PurgePac® base. A screw-jack system is provided for gap adjustment between ESID® rotor and the extraction bedplate. This could be done without opening the PurgePac® by adjusting the entire pillow block shaft mechanism from the outside of the tub. |
|||||
|
|||||
INSTALLATION Foundation Bolts
The certified drawing shows
the foundation bolt size and pitches. It is recommended that foundation
bolts be set in suitable sized pockets. Install the PurgePac 1000 by lowering it with the foundation bolts attached to the base such that the bolts enter the prepared pockets. Leveling blocks should be placed in position and the machine approximately leveled before the foundation bolts are finally grouted. DO NOT complete the grouting
of the machine at this stage until the machine has been finally leveled.
Allow sufficient time for the grout around the foundation bolts to
set before accurately aligning and leveling the machine. Check that
all foundation bolts are correctly tightened, machine align and leveled.
If these are satisfactory, proceed with grouting the machine.
Piping Connect the inlet, reject,
discharge and dilution pipework. It is essential that all piping be
well supported so that no strain is placed on the PurgePac. Consideration
should be given to providing loose flanges on pipes that bolt onto
the PurgePac. These loose flanges may be welded to the pipe after
the holes are seen to match. Use ¼" (6 mm) rubber jointing. Mount the motor on the
motor support (if motor was not supplied with the unit). Install the
pulley on the motor shaft and align it with the pulley on the PurgePac®
1000 drive shaft. Assemble the v-belts and adjust for proper tension
Check the clearance between
the rotor and the perforated plate; this would be 1.0 to 1.5mm. While the top cover is
off the DetrashPac, jog the motor to check the rotation. The ESID®
rotor should turn counter-clockwise when viewed from the top. Bottom Accept Valve The handwheel-operated
slide valve should be always opened. Opening rate of valve is according
to reject flow OPERATION Check the PurgePac® 1000 body for absence of foreign material like rags, tools, etc. Flush out the pipework and the machine using clean water. Check for correct operation of valves and water feeds. Check for correct motor rotation. Check detrashing control for correct sequencing. First Time Start-upa.) Open the accepts valve and the reject valve by 50%. b.) Open sealing water line and regulate flow. c.) Start the PurgePac® I drive motor. d.) Set the detrashing control panel. e.) Adjust the accepts valve to give the required flow. f.) Make sure the rejects are flowing. The inlet pressure should be 1.5 to 2 bars. g.) The flow resulting
from the accepts valve should maintain the pressure within the detrasher
and ensure it is completely filled with stock. Normal Start-up Sequence a.) Open the sealing water line. b.) Start the detrasher motor. c.) Set the detrashing
control panel to Auto.
|
|||||
|
|||||
Copyright
© 2003 H. T. Engineering works |